This beautiful outdoor concert venue was in need of a new sheet metal roof in order to repair some leaking & dry rot issues. The work consisted of bending the sheet metal & placing it onto the roof. This proved to be incredibly challenging due to the shape & height of the roof structure. We also refinished the concrete columns & modified the drainage. Spray on insulation was added underneath the roof.

The extreme difficulty of this project gave us, yet, another opportunity to show our expertise in working with unique projects that require a high level of skill & precision.

 

 

Specs:

Client: City of Eugene
Location: Eugene, OR
Architect: L.A. Kersch Architecture
Cost: $554,000
Completion: April 2014

Current Project

Oakridge Junior/Senior High and Elementary School
McKenzie Commercial CM/GC team built the Oakridge School District construction team through a low bid competitive pricing approach. Utilizing a fast-track approach, the project team substantially completed 65% of the project during the summer break in the academic calendar. Read more...

Oakridge

Latest News

AIA Construction Craft Award
Gordon Rea was awarded the American Institute of Architects Construction Craft Award at the May 8, 2019 award ceremony. The AIA honored the most deserving of contractors and other industry individuals for their superior skills, attentive effort and those that have mastered the ideals of craftsmanship. Read More...

AIA Construction Craft Award

Featured Project

Mapleton Elementary and High School
McKenzie Commercial puts their many years of experience with CM/GC projects to work. Before construction got underway, we helped implement almost $400,000 in value-engineering savings, and have phased this project in accordance with the school year to keep the building occupied and preserve school activities. Read more...

Mapleton

Current Project

Oakridge Junior/Senior High and Elementary School
McKenzie Commercial CM/GC team built the Oakridge School District construction team through a low bid competitive pricing approach. Utilizing a fast-track approach, the project team substantially completed 65% of the project during the summer break in the academic calendar. Read more...

Oakridge

Latest News

AIA Construction Craft Award
Gordon Rea was awarded the American Institute of Architects Construction Craft Award at the May 8, 2019 award ceremony. The AIA honored the most deserving of contractors and other industry individuals for their superior skills, attentive effort and those that have mastered the ideals of craftsmanship. Read More...

AIA Construction Craft Award

Featured Project

Mapleton Elementary and High School
McKenzie Commercial puts their many years of experience with CM/GC projects to work. Before construction got underway, we helped implement almost $400,000 in value-engineering savings, and have phased this project in accordance with the school year to keep the building occupied and preserve school activities. Read more...